Priors Orchard Week #3

Posted on 3rd July 2017

03/07/17Priors Orchard Week #3

The team continues to make good progress at Seaward’s new development in Southbourne with the road construction well under way.  Tarmac is due to be laid on 4th July.

Last week the sub-structure blockwork, internal drainage and services for Plots 1, 2, 3, 4, 5 and 6 were completed ready for the beam and block floor this week.

To register your early interest in this development please complete the contact form here or telephone us on 01243 790581.